The long-pending Belagavi–Dharwad railway line project via Kittur has received a significant boost after the Karnataka government released ₹70 crore toward land acquisition compensation. The district administration has commenced the phased transfer of compensation funds directly into the bank accounts of eligible landowners and farmers across the region.
The release of funds marks critical progress for the project, which had experienced delays due to pending land acquisition formalities and local alignment disputes.
Complete Project Details & Technical Specifications
| Parameter | Project Detail |
|---|---|
| Project Name | Belagavi–Dharwad Railway Line via Kittur |
| Total Track Length | 73.10 km |
| Initial Estimated Cost | ₹927.40 crore (subject to upward revision due to delay and land costs) |
| Cost Sharing Model | 50:50 joint venture between the Union Ministry of Railways and the Government of Karnataka |
| Total Land Required | ~1,588.79 acres (~581 hectares) across Belagavi and Dharwad districts |
| Executing Agency | South Western Railway (SWR) |
| Distance Reduction | Cuts rail distance between Belagavi and Dharwad by 31 km |
| Travel Time Impact | Eliminates the detour via Londa, saving nearly 1.5 to 2 hours of transit time |
Proposed Stations along the Route
The project will feature 11 railway stations in total, integrating 4 existing stations and 7 new stations:
- Existing Stations (4): Belagavi, Desur, Kyarakoppa, and Dharwad.
- New Stations (7): Kanvikarvinkoppa, Bagewadi, MK Hubballi, Hulikatti, Kittur, Teguru, and Mummigatti.
Land Acquisition Status & Farmer Relief
Farmers whose agricultural land is being acquired have consistently demanded timely and adequate compensation. Organizations representing local farmers urged state authorities to expedite payments to mitigate the financial burden on families forfeiting fertile holdings.
While land acquisition encountered opposition earlier this year in villages such as Idalhond, Nagenahalli, K.K. Koppa, Gurlgunji, Nandihalli, and Halgimardi—where residents requested alignment modifications—district officials conducted stakeholder consultations to resolve grievances before proceeding with disbursements.
Belagavi Deputy Commissioner Mohammad Roshan confirmed that the ₹70 crore disbursed by the state is being directly deposited into farmers’ bank accounts. Additional funds for remaining landowners are expected to be allocated shortly.
Regional & Infrastructure Impact
- Direct Connectivity: The new line replaces the circuitous route via Londa, connecting Belagavi, Kittur, and Dharwad directly along the industrial and agricultural corridors parallel to the Pune–Bengaluru National Highway (NH-48).
- Enhanced Express Operations: The upgraded alignment will enable higher operating speeds and create capacity for premium passenger operations, including Vande Bharat Express services.
- Economic Growth: Direct connectivity will facilitate faster passenger transit and freight movement, stimulating trade and industrial growth across North Karnataka.